A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?
Agratsant
4 months agoWWu
5 months, 3 weeks agoWakeupsid
5 months, 3 weeks agoKim222
10 months, 4 weeks agoMartinussantika
1 year agoompk
1 year, 1 month agoRezaee
1 year, 3 months agoBruce_Liu
1 year, 5 months agojosephsafiran
1 year, 5 months agoUncle_Lucifer
1 year, 7 months agoLucky_Cindy
1 year, 8 months agoOnly12go
1 year, 8 months agoadingmaki
1 year, 8 months agoFyrus
1 year, 9 months agokhaleghi
1 year, 10 months agovictory108
1 year, 10 months agoAish_
1 year, 10 months ago