exam questions

Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

Exam PMI-PBA topic 1 question 79 discussion

Actual exam question from PMI's PMI-PBA
Question #: 79
Topic #: 1
[All PMI-PBA Questions]

A project that was ongoing well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.
This could have been avoided if:

  • A. the customer met with regulatory authorities to verify that their requirements were also considered.
  • B. a change control process for requirements and their statuses was followed.
  • C. the project manager circulated the meeting minutes after the discussions with all the attendees.
  • D. the project team documented customer requests and obtained sign-off.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlphaD
6 months, 3 weeks ago
B is the best answer
upvoted 2 times
...
giushki
8 months, 3 weeks ago
Selected Answer: B
The situation could have been avoided if option B, "a change control process for requirements and their statuses was followed." A change control process for requirements and their statuses is a formal process for managing changes to project requirements. This process typically includes identifying the requirements that need to be changed, documenting the proposed changes, evaluating the impact of the changes, obtaining approval for the changes, and implementing the changes.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...