What should the business analyst do during the first steps of a project?

  • A. Align the sponsor expectations along the project goals.
  • B. Identify stakeholders and their interests.
  • C. Identify the classes of users and their requirements.
  • D. Evaluate the sources for requirements and prioritize them.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
giushki
7 months, 1 week ago
Selected Answer: B
The business analyst plays a critical role in the early stages of a project to ensure its success. During the first steps of a project, the business analyst should: B. Identify stakeholders and their interests.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago