exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 369 discussion

Actual exam question from PMI's PMI-RMP
Question #: 294
Topic #: 1
[All PMI-RMP Questions]

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about US$1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

  • A. The cost control processes are ineffective.
  • B. The cost baseline is inaccurate.
  • C. The actual reported costs are inaccurate.
  • D. The cost related risks are effectively managed.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: A
Think the same
upvoted 1 times
...
Azharmak
1 year ago
CPI less than 1 means poor cost control and over spending. Thus its A
upvoted 1 times
...
emikhael
1 year, 8 months ago
Selected Answer: A
The CPI is less than 1 which means that the cost risk management is not effective and the project is running over budget
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...