A = correct (if "On" means that the actual work is on the ideal burndown - everything is as planned and on time)
Actual Work Line is above the Ideal Work Line = If the actual work line is above the ideal work line, it means that there is more work left than originally predicted and the project is behind schedule.
Actual Work Line is below the Ideal Work Line = If the actual work line is below the ideal work line, it means that there is less work left than originally predicted and the project is ahead of schedule.
https://clickup.com/blog/burndown-charts/
Option C.
If the burndown line is trending above the ideal line, it means the team is ahead of schedule and may have completed the work before the iteration ends (option A). If the burndown line is trending below the ideal line, it means the team is behind schedule and may not be able to complete all the work within the iteration timebox (option C).
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Haffez
6 months, 4 weeks agotThye
1 year, 11 months agoAzharmak
2 years agoMinhha3
2 years, 1 month agoPetrevski
2 years, 1 month agoSmokeyofficiial
2 years, 2 months agoPetrevski
2 years, 1 month agonzk30
2 years ago