Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
havibaby
1 month agoPrincessviv96
2 months, 3 weeks agohrson81
4 months, 4 weeks agoK91
5 months, 3 weeks agoMSM
6 months agobetterthanyesterday
7 months, 1 week ago6114c29
8 months, 1 week agoQuaTV
9 months, 3 weeks ago723b698
1 year agoKENKEM
1 year, 1 month agokmsinthesky
1 year, 1 month agod482858
1 year, 2 months agoLucky_Cindy
1 year, 9 months agojukaz365
1 year, 9 months agoGoku_PMP
1 year, 10 months agoAsakthi
1 year, 10 months agoMuntadher
1 year, 11 months ago