Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
QuaTV
Highly Voted 11 months, 1 week agohavibaby
Most Recent 2 months, 3 weeks ago8a6d137
1 month agoPrincessviv96
4 months, 1 week agohrson81
6 months, 2 weeks agoK91
7 months, 1 week agoMSM
7 months, 3 weeks agobetterthanyesterday
8 months, 4 weeks ago6114c29
9 months, 3 weeks ago723b698
1 year, 2 months agoKENKEM
1 year, 3 months agokmsinthesky
1 year, 3 months agod482858
1 year, 4 months agoLucky_Cindy
1 year, 10 months agojukaz365
1 year, 11 months agoGoku_PMP
2 years agoAsakthi
2 years agoMuntadher
2 years ago