exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 102 discussion

Actual exam question from PMI's PMP
Question #: 102
Topic #: 1
[All PMP Questions]

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?

  • A. Performed a stakeholder analysis when the sponsor joined the project
  • B. Held a governance meeting to review the project increment
  • C. Escalated the issue to ensure the increment would be approved
  • D. Conducted a product iteration review with the new project sponsor
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
1 month ago
Selected Answer: D
The new project sponsor should have been engaged early and key aspects of the project explained in granular detail to avoid misalignment.
upvoted 1 times
...
hrson81
3 months, 1 week ago
Selected Answer: A
Typically, project sponsors do not participate in iteration reviews. There was no reason for the project manager to involve the sponsor in the review. Instead, if a proper stakeholder analysis had been conducted, it would have been possible to understand what the sponsor is interested in and how to communicate with them effectively.
upvoted 1 times
...
K91
4 months ago
Selected Answer: A
Although I'm not sure how A can solve the issue, D isn't very correct either. If it is an agile project and the sponsor has power to reject the artifacts, it's really weird to assume s/he didn't attend iteration review meetings.
upvoted 1 times
...
MSM
4 months, 1 week ago
Selected Answer: A
whether its predictive or agile stakeholder engagement is important so according to me A is the most appropriate answer as sponsor is replaced and the question says he was not previously engaged so without engaging him how can one call for iteration review so answer A is the correct one.
upvoted 1 times
...
betterthanyesterday
5 months, 2 weeks ago
Selected Answer: D
The "Stakeholder analysis" is gathering information to determine whose interests should be taken into account. I still don't understand how it could've helped avoid the situation.
upvoted 2 times
...
6114c29
6 months, 2 weeks ago
Selected Answer: D
D is to preventing
upvoted 2 times
...
QuaTV
8 months ago
Selected Answer: A
I chose D. But after read the correct answer and question. the question focuses on preventing this situation from happening in the future, rather than finding a solution to the current problem. With this mindset, "A. Performed a stakeholder analysis when the sponsor joined the project" is indeed worth considering.
upvoted 4 times
...
723b698
10 months, 4 weeks ago
Selected Answer: D
D is answer.
upvoted 3 times
...
KENKEM
11 months, 4 weeks ago
D is definitely the correct option.
upvoted 1 times
...
kmsinthesky
1 year ago
Selected Answer: D
D. Conducted a product iteration review with the new project sponsor
upvoted 3 times
...
d482858
1 year ago
This is not a predictive approach so stakeholder analysis is not needed. The question says it’s an incremental approach so the project sponsor should have attended review. Making D the correct answer.
upvoted 1 times
...
Lucky_Cindy
1 year, 7 months ago
Selected Answer: A
A. Performed a stakeholder analysis when the sponsor joined the project
upvoted 2 times
...
jukaz365
1 year, 8 months ago
D. New sponsor needs to be brought up to speed to get aligned. Stakeholder analysis was done. Only new sponsor has misalignment. D is the best way to handle this.
upvoted 3 times
...
Goku_PMP
1 year, 8 months ago
Selected Answer: D
review of iteration will help in aligning new sponsor with the deliverable of the current iteration
upvoted 1 times
...
Asakthi
1 year, 9 months ago
D do a iteration with sponsor
upvoted 1 times
...
Muntadher
1 year, 9 months ago
Selected Answer: A
if he have done Stakeheloder analysis this peer was suppose to be informed and engaged so A
upvoted 2 times
...
victory108
1 year, 11 months ago
Selected Answer: A
A. Performed a stakeholder analysis when the sponsor joined the project
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago