Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
Princessviv96
1 month agohrson81
3 months, 1 week agoK91
4 months agoMSM
4 months, 1 week agobetterthanyesterday
5 months, 2 weeks ago6114c29
6 months, 2 weeks agoQuaTV
8 months ago723b698
10 months, 4 weeks agoKENKEM
11 months, 4 weeks agokmsinthesky
1 year agod482858
1 year agoLucky_Cindy
1 year, 7 months agojukaz365
1 year, 8 months agoGoku_PMP
1 year, 8 months agoAsakthi
1 year, 9 months agoMuntadher
1 year, 9 months agovictory108
1 year, 11 months ago