Question #: 191
Topic #: 1
[All PMI-RMP Questions]

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

  • A. Risk acceptance
  • B. Risk transfer
  • C. Risk avoidance
  • D. Risk mitigation
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheAWSGuru
6 months, 2 weeks ago
B is correct
upvoted 1 times
...
Lunk
1 year, 2 months ago
Selected Answer: B
The question defines transfer - B
upvoted 1 times
...
aws_guru1
1 year, 8 months ago
B = Transfer is the correct answer.
upvoted 1 times
...
emikhael
1 year, 8 months ago
Selected Answer: B
too risky to do it internally and hiring a contractor, then it is a transfer.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...