exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 331 discussion

Actual exam question from PMI's PMP
Question #: 331
Topic #: 1
[All PMP Questions]

A project manager discovers that the project team is spending a large amount of time delivering several reporting formats for the same project updates to multiple stakeholders.
What should the project manager do to reduce the time spent on these activities?

  • A. Update the communications management plan to remove less influential stakeholders.
  • B. Delegate all of the stakeholder communications activities to a project team member.
  • C. Segment the types of communications to be delivered to different stakeholders.
  • D. Hold biweekly status meetings to deliver information to all stakeholders at once.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
victory108
8 months, 1 week ago
Selected Answer: C
C. Segment the types of communications to be delivered to different stakeholder
upvoted 1 times
...
TONYJAVI
9 months ago
Selected Answer: C
Totally C.
upvoted 1 times
...
Alizade
1 year, 1 month ago
Selected Answer: C
The project manager should segment the types of communications to be delivered to different stakeholders based on their interest and need for information. Not all stakeholders require the same level of detail or frequency of updates. This approach will reduce the time spent by the project team in delivering several reporting formats for the same project updates to multiple stakeholders, while still ensuring that all stakeholders are informed and engaged appropriately. It is important to update the communications management plan to reflect this new approach.
upvoted 4 times
Hung1
1 year ago
Option D, holding biweekly status meetings to deliver information to all stakeholders at once, may not be the best solution as some stakeholders may require more frequent updates or more specific information than what can be delivered in a general status meeting.
upvoted 1 times
...
...
Hung3102
1 year, 1 month ago
By segmenting the types of communication, the project manager can tailor the updates to each stakeholder group's needs and reduce the time spent on creating multiple reporting formats. This approach ensures that stakeholders receive relevant information and prevents them from receiving unnecessary information that could lead to confusion or disinterest.
upvoted 3 times
Hung1
1 year ago
Option D, holding biweekly status meetings to deliver information to all stakeholders at once, may not be the best solution as some stakeholders may require more frequent updates or more specific information than what can be delivered in a general status meeting.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago