exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 346 discussion

Actual exam question from PMI's PMP
Question #: 346
Topic #: 1
[All PMP Questions]

A project manager is leading an electrical project that spans five towns. The project manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?

  • A. Engage with the town's authorities to discuss the reason for the change in commitment and agree on a solution.
  • B. Instruct the team to move to the next town and continue the project to avoid further delays.
  • C. Change the project scope and seek approval to exclude this town from the overall project.
  • D. Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: A
A. Engage with the town's authorities to discuss the reason for the change in commitment and agree on a solution
upvoted 1 times
...
victory108
9 months, 1 week ago
Selected Answer: A
A. Engage with the town's authorities to discuss the reason for the change in commitment and agree on a solution
upvoted 1 times
...
Alizade
1 year, 1 month ago
Selected Answer: A
The best course of action for the project manager in this situation would be option A: Engage with the town's authorities to discuss the reason for the change in commitment and agree on a solution. Engaging with the town's authorities can help the project manager understand why the town is not allowing the team to work there and find a solution that is acceptable to both parties. It is possible that there has been a change in the town's circumstances that has led to the change in commitment, and this needs to be understood and addressed.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...