A new engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting. What should the project manager do?
A.
Obtain related training for the new team member.
B.
Determine the appropriate level of decision-making authority and empower the engineer.
C.
Make all of the decisions for the engineer in order to keep the workflow on track.
D.
Replace the resource with an experienced engineer.
The best course of action for the project manager in this situation would be option B: Determine the appropriate level of decision-making authority and empower the engineer.
B. Determine the appropriate level of decision-making authority and empower the engineer
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Alizade
Highly Voted 1 year, 1 month agoLucky_Cindy
Most Recent 7 months agovictory108
9 months, 3 weeks ago