Question #: 230
Topic #: 1
[All PMP Questions]

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member's deliverables do not meet the requirements.
What should the project manager do first?

  • A. Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables are submitted.
  • B. Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.
  • C. Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework the deliverables.
  • D. Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: B
B. Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding
upvoted 1 times
...
victory108
10 months, 2 weeks ago
Selected Answer: B
B. Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding
upvoted 1 times
...
SteAle
11 months ago
Selected Answer: B
The PM needs to understand why this is happening by discussing the process resulted in the creation of the noncompliant deliverables
upvoted 1 times
...
Alizade
1 year, 1 month ago
Selected Answer: B
When team members' deliverables do not meet the requirements, it is essential to identify the root cause of the issue and work with the team to find a solution. In this case, discussing the process used to create the noncompliant deliverables with the project team can help the project manager identify potential misunderstandings and work with the team to address any gaps in their understanding of the requirements. This approach will help improve the team's overall performance, increase their engagement, and reduce the likelihood of similar issues occurring in the future.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...