Exam PMP topic 1 question 731 discussion

Actual exam question from PMI's PMP
Question #: 731
Topic #: 1
[All PMP Questions]

A project manager is leading a project team composed of members with varying levels of knowledge and experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.

What should the project manager do?

  • A. Ask the less-experienced members to perform tasks exactly as they are instructed by the experienced members.
  • B. Ask each experienced member to be the mentor to one of the less-experienced members.
  • C. Ask the more experienced members to review all of the tasks performed by the less-experienced members.
  • D. Ask the resource manager to replace the less-experienced members with more experienced team members.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Alizade
Highly Voted 1 year, 1 month ago
Selected Answer: B
B. Ask each experienced member to be the mentor to one of the less-experienced members. In this situation, the project manager should leverage the expertise of the experienced team members to mentor and guide the less-experienced team members. This will not only ensure that everyone on the team is working together towards the same goal, but it will also provide an opportunity for knowledge sharing and skills development within the team. The project manager can facilitate this by assigning pairs of experienced and less-experienced team members to work together on specific tasks or areas of the project, and by encouraging open communication and collaboration between all team members. Replacing team members is not necessary as long as they are willing and able to learn and improve with the guidance of their more experienced colleagues.
upvoted 5 times
...
victory108
Most Recent 7 months ago
Selected Answer: B
B. Ask each experienced member to be the mentor to one of the less-experienced members
upvoted 1 times
...
Inzaghi78
8 months, 2 weeks ago
Select B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.