exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 302 discussion

Actual exam question from PMI's PMP
Question #: 302
Topic #: 1
[All PMP Questions]

The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.
What should the project manager do?

  • A. Promote engineer B instead since the project manager has the authority to make this decision.
  • B. Help engineer A to become familiar with this new role and ensure engineer B stays motivated.
  • C. Coach engineer B to be prepared to perform this role if and when engineer A fails.
  • D. Request management approval that engineer B will be promoted if engineer A fails in this role.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 month ago
Selected Answer: B
PM have no right to promote , its depend on executive
upvoted 1 times
...
Lucky_Cindy
6 months, 1 week ago
Selected Answer: B
B. Help engineer A to become familiar with this new role and ensure engineer B stays motivated
upvoted 1 times
...
victory108
8 months, 3 weeks ago
Selected Answer: B
B. Help engineer A to become familiar with this new role and ensure engineer B stays motivated
upvoted 1 times
...
Alizade
1 year, 1 month ago
Selected Answer: B
B. Help engineer A to become familiar with this new role and ensure engineer B stays motivated. Given that management's decision remains unchanged, the project manager should respect the decision and work to support engineer A in their new role as team lead. This includes helping them become familiar with their new responsibilities and providing any necessary coaching or guidance. Additionally, the project manager should ensure that engineer B stays motivated and engaged by recognizing their contributions and providing them with opportunities for growth and development within the project. This approach promotes a positive working environment and supports the overall success of the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.