In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.
What should the project manager do next?

  • A. Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.
  • B. Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.
  • C. Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.
  • D. Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Alizade
7 months, 1 week ago
Selected Answer: A
The correct answer is: A. Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.
upvoted 1 times
...
victory108
8 months, 2 weeks ago
Selected Answer: A
A. Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed
upvoted 1 times
...
PMPExpert
11 months, 2 weeks ago
Selected Answer: A
Option A is the Best option as it address the problem. Option B There are some team members who are doing good hence it would be unfair to them Option C Stopping others sounds negative Option D Retrain "All" is not rational
upvoted 2 times
...
Alizade
1 year, 1 month ago
Selected Answer: A
A. Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed. It's important for the project manager to acknowledge and recognize the team's efforts in self-organizing and growing, as this promotes a positive team culture. The project manager should then work with the facilitators who are struggling to identify areas of improvement and provide one-on-one coaching or additional training as needed. It's important to maintain the team's autonomy in choosing facilitators and continue to encourage growth and improvement.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago