A project manager is leading a large public project that will have a high impact on the town's citizens.
How should the project manager define the different requirements?

  • A. Analyze the interests and influence of stakeholders and evaluate their requirements.
  • B. Include only the key requirements and keep the stakeholders informed about scope decisions.
  • C. Add only the opinions of the team, because they know the objectives of the project.
  • D. Include only the common requirements of each stakeholder group in the project goals.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: A
A - Analyze the interests and influences of stakeholders
upvoted 1 times
...
Parithi
9 months, 1 week ago
A - Analyze the interests and influences of stakeholders
upvoted 1 times
...
victory108
9 months, 1 week ago
Selected Answer: A
A. Analyze the interests and influence of stakeholders and evaluate their requirements
upvoted 1 times
...
Alizade
1 year, 1 month ago
Selected Answer: A
A. Analyze the interests and influence of stakeholders and evaluate their requirements. In a large public project, it's important to consider the requirements of all stakeholders, including the citizens who will be impacted by the project. Analyzing the interests and influence of stakeholders and evaluating their requirements will help ensure that the project meets the needs of the community it serves. It's important to involve stakeholders in the project planning and decision-making process to increase the chances of project success and community support.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...