exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 40 discussion

Actual exam question from PMI's PMI-RMP
Question #: 40
Topic #: 1
[All PMI-RMP Questions]

Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan.
What should the risk manager do first?

  • A. Meet with the project team.
  • B. Inform management of out-of-scope work.
  • C. Review activities for new risks.
  • D. Review the change control log.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AllPMI
7 months ago
The correct answer is D: Review the Change Control Log Since the activities weren’t in the original plan, so these activities are added to the plan by change requests. The best choice is “review the change log” to know the detail of the changes.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago