Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan. What should the risk manager do first?
The correct answer is D: Review the Change Control Log
Since the activities weren’t in the original plan, so these activities are added to the plan by change requests. The best choice is “review the change log” to know the detail of the changes.