exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 169 discussion

Actual exam question from PMI's PMI-RMP
Question #: 169
Topic #: 1
[All PMI-RMP Questions]

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

  • A. Take note of the extensive impact of these risks in the risk register
  • B. Address the unique characteristics of these risks on a case-by-case basis
  • C. Include an escalation process in the risk management plan
  • D. Contact the risk managers of the other projects and inform them
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: C
Escalation process includes also communication. The difference lies in formalized procedure or not of doing it. You just can inform other risk managers or create a formal escalation process where it is documented how to approach to this kind of situations; and then, do the escalation = inform.
upvoted 1 times
...
AllPMI
1 year, 8 months ago
Escalation is appropriate when the project team or the project sponsor agrees that a threat is outside the scope of the project or that the proposed response would exceed the project manager’s authority. Escalated risks are managed at the program level, portfolio level, or other relevant parts of the organization, and not at the project level. The project manager determines who should be notified about the threat and communicates the details to that person or part of the organization. It is important that ownership of escalated threats is accepted by the relevant party in the organization. Threats are usually escalated to the level that matches the objectives that would be affected if the threat occurred. Escalated threats are not monitored further by the project team after escalation, although they may be recorded in the risk register for information. PMBOK6 Page# 442.
upvoted 3 times
...
AllPMI
1 year, 8 months ago
Correct answer should be 'C' The risk management plan includes the tailored risk management processes, which are based on the process maturity of the organization. Scalable elements of the process that are a part of risk management planning include, but are not limited to: Available resources, Escalation paths, Methodology and processes used, Tools and techniques used, Supporting infrastructure, Review and update frequency, Reporting requirements. The reference is the standard for risk management in portfolios, programs, and projects page#31.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...