Exam PMP topic 1 question 723 discussion

Actual exam question from PMI's PMP
Question #: 723
Topic #: 1
[All PMP Questions]

A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule. with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.

What should the project manager do first?

  • A. Review the lessons learned register with the former project manager in a private meeting.
  • B. Meet the project team to assert authority and reassign the project tasks for a timely delivery.
  • C. Review the project schedule and ask for the contingency reserve to crash the project.
  • D. Meet the project team and stakeholders to identify the root cause of the issue and develop a solution.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: D
D. Meet the project team and stakeholders to identify the root cause of the issue and develop a solution
upvoted 1 times
...
SteAle
9 months, 1 week ago
Selected Answer: D
Firstly, the PM needs to find out the root cause of the issues between the team and the previous PM to avoid stepping on the same rake
upvoted 2 times
...
Faozi
11 months, 2 weeks ago
Why not C? Because according to the question, the previous PM, had numerous complaints with the team. So the root cause was known.
upvoted 1 times
AstridN
11 months ago
Hmmm... I think it wwas more like to know the root cause of the complaints..not that the complaints are the root cause
upvoted 1 times
...
Jamrock
8 months, 1 week ago
they ask what to do first. so meet to discuss fist. and the next step may be C. but first is D.
upvoted 1 times
...
...
JYKL88
1 year, 1 month ago
D. Meet the project team and stakeholders to identify the root cause of the issue and develop a solution. As the new project manager, the first step should be to understand the situation and the reasons behind the delays. Meeting with the project team and stakeholders will provide insights into the causes of the conflicts and potential issues with the project. Once the root cause is identified, the project manager can work with the team to develop a solution to get the project back on track and ensure timely delivery
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.