Exam PMP topic 1 question 657 discussion

Actual exam question from PMI's PMP
Question #: 657
Topic #: 1
[All PMP Questions]

A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?

  • A. Discuss ground rules with the team that will include daily meetings.
  • B. Agree on a new time and reschedule the daily standups.
  • C. Use one-to-one virtual meetings because they are more efficient.
  • D. Ask senior management for coaching regarding this situation.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
UppersquareCapital
2 weeks, 3 days ago
Selected Answer: B
B. Agree on a new time and reschedule the daily standups.
upvoted 1 times
...
victory108
7 months, 1 week ago
Selected Answer: A
A. Discuss ground rules with the team that will include daily meetings
upvoted 2 times
...
SteAle
9 months, 1 week ago
Selected Answer: A
Why agree on a new time? It doesn't indicate the reason for team members missing the daily standups. First, the PM needs to discuss ground rules.
upvoted 2 times
...
JYKL88
1 year, 1 month ago
B. Agree on a new time and reschedule the daily standups. If half of the team members regularly join late or miss virtual daily standup meetings, it is important to find a solution to ensure that the team stays up-to-date with the progress of the project. One approach is to agree on a new time and reschedule the daily standups, which may help to ensure that all team members can attend. The project manager can also discuss ground rules and expectations with the team to emphasize the importance of daily meetings and the impact of team members' late attendance or absence. Additionally, the project manager can review the project schedule to determine if any changes can be made to accommodate team members who may be in different time zones or who may have other scheduling conflicts.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...