A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
Only12go
Highly Voted 1 year, 2 months agoAnne99
Most Recent 2 months, 3 weeks ago462729f
4 months agokmsinthesky
7 months, 3 weeks agoAbdelmonm
11 months, 1 week agoodylec
1 year agoadingmaki
1 year, 2 months agoDavid983
1 year, 2 months agoadingmaki
1 year, 2 months agovictory108
1 year, 3 months agoNeil20
1 year, 6 months agokevzzz
1 year, 6 months agoThirukj
1 year, 6 months agoRevZig67
1 year, 8 months agoHung3102
1 year, 8 months agoAntony100
1 year, 8 months agoemelba
1 year, 9 months ago