A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
Only12go
Highly Voted 1 year agoAnne99
Most Recent 3 weeks, 6 days ago462729f
2 months agokmsinthesky
5 months, 3 weeks agoAbdelmonm
9 months, 1 week agoodylec
10 months, 2 weeks agoadingmaki
1 year agoDavid983
1 year agoadingmaki
1 year agovictory108
1 year, 1 month agoNeil20
1 year, 4 months agokevzzz
1 year, 4 months agoThirukj
1 year, 4 months agoRevZig67
1 year, 6 months agoHung3102
1 year, 6 months agoAntony100
1 year, 6 months agoemelba
1 year, 7 months ago