During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?
AbbasTaki
Highly Voted 2 years, 2 months agoSolid_Jehuty
Highly Voted 2 years, 4 months agocococua
Most Recent 2 weeks, 6 days agoAnne99
4 months, 1 week agoductrinh
4 months, 2 weeks agoshpunk
5 months, 3 weeks agovlxx
8 months, 3 weeks ago23169fd
10 months, 3 weeks agoBruce_Liu
1 year, 7 months agovictory108
1 year, 11 months agoAish_
2 years agoSteAle
2 years, 1 month agosassy2023
2 years, 1 month agoslick90
2 years, 2 months agoHung1
2 years, 3 months agoHung1
2 years, 3 months ago