During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?
AbbasTaki
Highly Voted 1 year, 11 months agoSolid_Jehuty
Highly Voted 2 years, 1 month agoAnne99
Most Recent 1 month agoductrinh
1 month agoshpunk
2 months, 1 week agovlxx
5 months, 1 week ago23169fd
7 months, 2 weeks agoBruce_Liu
1 year, 3 months agovictory108
1 year, 8 months agoAish_
1 year, 8 months agoSteAle
1 year, 10 months agosassy2023
1 year, 10 months agoslick90
1 year, 10 months agoHung1
2 years agoHung1
2 years ago