A key project stakeholder showed interest in the beginning of a complex agile project, but has become less involved as the sprint has progressed due to additional responsibilities. A few sprints later, the key stakeholder rejected a feature deliverable. The team is reworking the rejected deliverable for the next sprint.
What should the project manager have done to avoid this situation?
d370e49
9 months, 2 weeks agoea4e1f8
9 months, 3 weeks agoKim222
10 months, 2 weeks agoBruce_Liu
1 year, 5 months agoPsadon
1 year, 6 months agoodylec
1 year, 6 months agoOnly12go
1 year, 8 months agoUppersquareCapital
1 year, 5 months agoadingmaki
1 year, 8 months agovictory108
1 year, 10 months agoAish_
1 year, 10 months agoJamrock
1 year, 10 months agoSteAle
1 year, 11 months agoRevZig67
2 years, 2 months agorajeshtk
2 years, 2 months agoJYKL88
2 years, 2 months agorajeshtk
2 years, 2 months agoJYKL88
2 years, 2 months ago