A food company is developing a new product using a predictive approach, and the product is currently in the testing phase. Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach. At the end of one of the iterations, a new regulation related to the product is enacted.
What should the project manager do next?
jazzuuu
2 months, 3 weeks agovlxx
8 months, 2 weeks agoea4e1f8
11 months, 2 weeks agotonybuivannghia
1 year agoompk
1 year, 2 months agojiwoon
1 year, 6 months agoRezaee
1 year, 6 months agoBruce_Liu
1 year, 6 months agoCommonNickname
1 year, 6 months agoUppersquareCapital
1 year, 7 months agoPsadon
1 year, 7 months ago6thEditionAndy
1 year, 8 months agoOnly12go
1 year, 9 months agovictory108
1 year, 11 months agoAish_
1 year, 12 months agokevzzz
2 years agomshad
2 years ago