Question #: 435
Topic #: 1
[All PMP Questions]

A project manager is managing an innovation project for a big corporation. The project manager is planning to use email as the main communication channel; however, the product owner prefers to use another approved communication tool instead of email.
What should the project manager do?

  • A. Contact the sponsor to request direction regarding the communication tool to be used by the project team
  • B. Update the communications management plan based on the product owner's preferences and distribute to the team
  • C. Suggest to the team to start using the communication tool suggested by the product owner
  • D. Request the product owner to use email because using another tool will increase the workload
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Anssoo
3 months, 1 week ago
Selected Answer: C
Answer is C. Without team discussion about communication tool, we can not update the communication tool. Suggestion for discussion initiation is required for this case.
upvoted 1 times
...
Only12go
9 months, 4 weeks ago
Selected Answer: B
B. Update the communications management plan based on the product owner's preferences and distribute to the team. Effective communication is crucial for project success. If the product owner, who is a key stakeholder, has a preference for a different communication tool that is already approved, it makes sense to accommodate this preference. By updating the communications management plan to reflect this preference, the project manager ensures that communications are aligned with stakeholder needs and that there's clarity on how information will be exchanged. This helps in fostering collaboration and ensuring everyone is on the same page.
upvoted 1 times
...
victory108
11 months, 3 weeks ago
Selected Answer: B
B. Update the communications management plan based on the product owner's preferences and distribute to the team
upvoted 1 times
...
Akhundzada
1 year ago
Selected Answer: C
Effective communication is crucial in project management, and it's important to consider the preferences and needs of stakeholders, including the product owner. If the product owner has a preferred communication tool that is approved and can better facilitate communication for the project, it's a good idea to consider adopting that tool. He is in the planning. There are not a plan for updating
upvoted 2 times
...
AstridN
1 year ago
Selected Answer: B
I'm going with B because this will be specific to the PO. It might be smth else for another stakeholder and it'll br captured as well
upvoted 2 times
...
SteAle
1 year, 1 month ago
Selected Answer: B
The stakeholders' comm preferences should be captured in the comm management plan
upvoted 2 times
...
clarksu
1 year, 3 months ago
Selected Answer: A
why the product owner's opinion on this becomes the choice of team? How would sponsors to communicated with this PO?
upvoted 1 times
clarksu
1 year, 3 months ago
I am sorry, I was wrong. this scenario should be B. It is OK to use approved channels.
upvoted 5 times
...
...
hardy007
1 year, 4 months ago
i think D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...