A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact project implementation. What should the project manager do next?
A.
Assign an additional resource to help the team member with the tasks
B.
Ask the team member's functional manager if there are any known issues
C.
Convene a team meeting to encourage and motivate the entire team
D.
Meet with the team member to understand their concerns and/or issues
In my view I would first have a one on one discussion with the team member to better understand why they are missing their deadlines and from gaining that understanding may suggest adding an additional resource to assist with task if need be.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Princessviv96
4 months, 2 weeks agoductrinh
4 months, 4 weeks agomartinx84
1 year, 1 month agoLucky_Cindy
1 year, 11 months agoMuntadher
2 years agovictory108
2 years, 2 months agoMobarak7
2 years, 4 months ago