exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 116 discussion

Actual exam question from PMI's PMP
Question #: 116
Topic #: 1
[All PMP Questions]

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status.
What should the project manager do first?

  • A. Meet with the team and decide the type and frequency of the reports to send to the CEO
  • B. Send the CEO one executive summary per week instead of five reports per week
  • C. Review the communications management plan
  • D. Review the stakeholder engagement plan.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
1 month ago
Selected Answer: D
in this scenario start by reviewing the stakeholder engagement plan then instead of sending five reports you can send one executive summary with key information that the CEO wants to know about the project
upvoted 1 times
...
K91
3 months, 3 weeks ago
Selected Answer: C
Communications management plan Communications management plan is about "how to communicate", while stakeholder engagement plan is about "who stakeholders are", "how important they are", "how influential they are", "what expectations they have" etc. Stakeholder engagement plan may have some information about communication, but it's not the main part.
upvoted 1 times
...
Yak_Yeti
4 months, 1 week ago
Selected Answer: D
The communications management plan defines the overall communication strategy for the project. While it's important, the stakeholder engagement plan is more specific to individual stakeholder needs. The CEO's complaint is a stakeholder-specific issue, making the stakeholder engagement plan the more appropriate first point of review.
upvoted 1 times
...
kavikris
5 months, 1 week ago
Selected Answer: A
Before reviewing the communication plan, first thing to do is to meet what reports are relevant for the CEO and in what frequency to be sent then the communications plan can be updated accordingly
upvoted 1 times
kavikris
5 months, 1 week ago
moreover, if the communication plan contains strategies for 100 stakeholders , the project manager cant review for all customers when the problem is for one stakeholder right?
upvoted 1 times
...
...
23169fd
7 months, 3 weeks ago
Selected Answer: C
The purpose of the Communication Management Plan is to ensure that all stakeholders receive timely and appropriate information. The purpose of the Stakeholder Engagement Plan is to proactively manage stakeholder expectations, foster positive relationships, and ensure stakeholders are informed, involved, and supportive of the project
upvoted 2 times
...
Amirsnsn
10 months, 2 weeks ago
Stakeholder has not been recognized properly. Therefore D
upvoted 1 times
...
diddydiddy
11 months ago
Selected Answer: D
Why not the stakeholder engagement plan? The stakeholder engagement plan outlines the communication plan for each stakeholder.
upvoted 4 times
...
Lucky_Cindy
1 year, 7 months ago
Selected Answer: C
Communication plan
upvoted 1 times
...
Asakthi
1 year, 9 months ago
C communication management plan to be updated
upvoted 1 times
...
victory108
1 year, 11 months ago
Selected Answer: C
C. Review the communications management plan
upvoted 1 times
...
Mobarak7
2 years ago
Selected Answer: C
Is true to fit stakeholder needs
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago