Exam PMP topic 1 question 124 discussion

Actual exam question from PMI's PMP
Question #: 124
Topic #: 1
[All PMP Questions]

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a requirement for a user experience design approach.
Which project management approach should the project manager use?

  • A. The software development has a high uncertainty level, so an agile approach is recommended for the project.
  • B. A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.
  • C. The deliverables are significantly different, so the project should be split into two projects that are driven by a program.
  • D. The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
4 months, 1 week ago
Selected Answer: B
B I believe the hybrid approach will suit this situation B. A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.
upvoted 1 times
...
kavikris
8 months, 2 weeks ago
Selected Answer: A
I am thinking , lets assume if the product is computer, then it can add value only when both hardware and software are delivered together right? how can software be released in agile way while the hardware can be released as single delivery only at the end of the project? so it has to be finish to finish in agile way?
upvoted 1 times
...
43a41d4
10 months ago
Selected Answer: B
B is the good answer
upvoted 1 times
...
Asakthi
2 years ago
B hybrid
upvoted 1 times
...
victory108
2 years, 2 months ago
Selected Answer: B
B. A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries
upvoted 1 times
...
Mobarak7
2 years, 4 months ago
Selected Answer: B
B for this question
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...