A project manager is assigned to manage a project for a previous client of the company. The project manager was warned that this client will likely try to add extra scope to the project without considering the impact of change on time, cost, quality, and risks.
Which action should the project manager take to help plan and manage the budget and resources?
Hung1
Highly Voted 1 year agoaqz_111
Highly Voted 1 year agopigmeatpig
Most Recent 1 month, 2 weeks agoLucky_Cindy
7 months, 1 week agoAsakthi
9 months agoAbbasTaki
11 months, 2 weeks agovictory108
11 months, 2 weeks ago