Actual exam question from PMI's PMP
Question #: 250
Topic #: 1
[All PMP Questions]

A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses predictive approaches, does not like virtual tools such as chats, task trackers, and so forth. They prefer email, telephone calls, and face-to-face meetings.
How should the project manager approach this situation?

  • A. Use regular screen-sharing sessions to show the progress to the stakeholder.
  • B. Align and agree with the stakeholder on the communication approach.
  • C. Ask the manager to use virtual communication tools and online dashboards.
  • D. Create a digital dashboard to meet the manager's information needs.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
10 months, 1 week ago
Selected Answer: B
B. Align and agree with the stakeholder on the communication approach
upvoted 1 times
...
Thirukj
11 months, 3 weeks ago
Answer is B, as interest of Stakeholder is paramount to project success
upvoted 1 times
...
Hung1
1 year, 1 month ago
The best approach in this situation is B. The project manager should try to align and agree with the stakeholder on the communication approach. It is essential to understand the stakeholder's perspective and preferences, and work together to find a communication approach that satisfies everyone. This can be done by having a conversation with the stakeholder and discussing the advantages and disadvantages of different communication methods. It is important to consider that stakeholders can have different levels of technical expertise and preferred modes of communication, and their opinions should be taken into account
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...