Exam PMP topic 1 question 703 discussion

Actual exam question from PMI's PMP
Question #: 703
Topic #: 1
[All PMP Questions]

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

  • A. Review the communications management plan to identify new stakeholders.
  • B. Define a risk management plan for the new approach, as needed.
  • C. Define a project management plan for the new approach, as needed.
  • D. Review the benefits realization plan to include the cost of the change.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kevzzz
Highly Voted 1 year ago
Selected Answer: D
PMBOK 7th Edition 2.7.2.5 Business Value
upvoted 6 times
...
Only12go
Most Recent 7 months ago
Selected Answer: D
Considering the need for informed decision-making and understanding the implications of changing approaches: D. Review the benefits realization plan to include the cost of the change. This option allows the organization to consider whether the change to a predictive approach will truly deliver the expected benefits or if the past negative experience was an outlier.
upvoted 2 times
...
adingmaki
7 months, 1 week ago
D from PMBOK
upvoted 1 times
...
victory108
7 months, 4 weeks ago
Selected Answer: C
C. Define a project management plan for the new approach, as needed
upvoted 1 times
...
zayn_1983
9 months, 3 weeks ago
Define a project management plan for the new approach is a premature action, so my answer is D
upvoted 1 times
...
Davonos
9 months, 3 weeks ago
I believe the answer should C The question is about development approach and not benefit realization
upvoted 1 times
...
SteAle
10 months ago
Selected Answer: D
D. Review the benefits realization plan to include the cost of the change
upvoted 2 times
...
Debugs_Bunny
1 year, 1 month ago
Selected Answer: C
C. Define a project management plan for the new approach, as needed. If the project board decides to replace Scrum with a predictive approach, the project manager should adapt the project management plan to reflect this change. This will involve updating the various components of the plan, such as scope, schedule, budget, and risk management, to accommodate the new approach. Additionally, the project manager should ensure that the team members and stakeholders are informed about the change and are aligned with the new methodology.
upvoted 2 times
fulcrum501
1 year ago
should not develop a new plan until the PMO office reaches a consensus. Creating a new plan without weighing the pros and cons can result in waste of resources.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...