exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 386 discussion

Actual exam question from PMI's PMP
Question #: 386
Topic #: 1
[All PMP Questions]

The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.
What should the project manager do?

  • A. Determine the risks and identify a resolution during the retrospective meeting.
  • B. Inform stakeholders about the delay during project updates.
  • C. Discover the gaps in the communications management plan and address them accordingly.
  • D. Determine cross-dependencies and plan a spike in the next sprint.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Anne99
3 weeks, 3 days ago
Selected Answer: D
A spike is a time-boxed research activity in Agile used to explore and gain the knowledge needed to reduce uncertainty. By: Identifying cross-dependencies Planning a spike …the team can better understand the problem, reduce future delays, and plan more effectively.
upvoted 1 times
...
9ca6412
2 months, 2 weeks ago
Selected Answer: D
Not agree that A right answer. Retrospective is time for discussing and reviewing our process. D looks lime more proactive approach
upvoted 1 times
...
23169fd
7 months, 1 week ago
Selected Answer: D
In Agile projects, a spike is a time-boxed research or prototyping activity aimed at resolving uncertainties or exploring solutions to complex issues. If user stories are taking longer than expected to be delivered, the project manager should investigate potential cross-dependencies or technical uncertainties that are causing delays. Planning a spike in the next sprint allows the team to focus on resolving these uncertainties, enabling smoother progress in future sprint
upvoted 1 times
...
rshankhwa
1 year, 2 months ago
Selected Answer: B
A. Wait until Retrospective meeting which usually happens on Sprint closure B. This can be quick as the updates can be provided in next stand up and resolution brainstorming can happen as well C. No mention of communication gaps D. No mention of cross-dependencies I would go with B
upvoted 1 times
...
josephsafiran
1 year, 3 months ago
Selected Answer: A
The project manager should choose option **A. Determine the risks and identify a resolution during the retrospective meeting**. This approach allows the team to reflect on what's working and what's not, and to come up with strategies for improvement. It's a key part of agile methodologies, which value learning and adaptation. If user stories are taking longer to deliver, it's important to understand why and to identify potential risks or obstacles. The retrospective meeting provides an opportunity to do this in a collaborative and constructive manner. Remember, effective project management involves not just managing tasks, but also learning and adapting along the way.
upvoted 2 times
...
Lucky_Cindy
1 year, 5 months ago
Selected Answer: A
A. Determine the risks and identify a resolution during the retrospective meeting.
upvoted 1 times
...
Only12go
1 year, 6 months ago
Selected Answer: A
A. Determine the risks and identify a resolution during the retrospective meeting. In an agile project, the retrospective meeting is a key forum for the project team to reflect on their work, identify issues, and propose improvements. If certain user stories are taking longer to be delivered, it's important for the project manager and the team to use the retrospective meeting to: Identify the specific risks or challenges associated with these user stories. Discuss and analyze the root causes of the delays. Propose and prioritize potential resolutions or improvements. Take action to address the identified issues and improve the team's efficiency in delivering user stories.
upvoted 2 times
...
kevzzz
1 year, 6 months ago
Selected Answer: A
Retrospectives are the structured reflective practice for the team to learn and improve their ways of working based on the experience of the past iteration. The purpose of retrospection is to examine the process the team uses, to build team commitment, and to transfer knowledge to the next iteration and possibly to other teams. https://www.pmi.org/disciplined-agile/product-owner/practice-iteration-retrospective
upvoted 1 times
...
Fyrus
1 year, 6 months ago
Selected Answer: A
I would go with A if no time is going to be taken during the retrospective to analyze risk. It should be already done to just address the problems in the retrospective, after, of course, talk about what went well and what didn't. Firstly I thought D but A seems better... It's a difficult one. Finally, ChatGPT said: • Retrospective Meeting: The retrospective meeting is a dedicated session where the team can reflect on the sprint, discuss what went well, what didn't, and identify opportunities for improvement. Analyzing the delays during this meeting can help the team understand the factors contributing to the delays and develop actionable solutions for future sprint
upvoted 2 times
...
victory108
1 year, 8 months ago
Selected Answer: D
D. Determine cross-dependencies and plan a spike in the next sprint
upvoted 2 times
...
Aesam
1 year, 9 months ago
https://scaledagileframework.com/spikes/
upvoted 1 times
...
Aesam
1 year, 9 months ago
Selected Answer: D
This looks like a a prototyping user story so a Spike can be added.
upvoted 1 times
...
SteAle
1 year, 9 months ago
Selected Answer: A
The purpose of retrospective meetings is to fix problems in the process.
upvoted 2 times
...
snagile
1 year, 12 months ago
Why not D.... Delay may be due to dependencies too
upvoted 2 times
...
RevZig67
2 years ago
Selected Answer: B
the best option in this case would be to inform stakeholders about the delay during project updates (Option B) and determine the reasons for the delay and develop a plan to address them. It is also essential to ensure effective communication with all stakeholders and update them accordingly.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago