During the final stage of the launch for a new design, team members are having a conflict about some features of the design. What should the project manager do?
A.
Call a stakeholder meeting along with team members and seek consensus.
B.
Ask stakeholders to reduce the scope in order to meet project deadlines.
C.
Ask the project sponsor to make the decision about the design features.
D.
Review the design with the team members and propose a new launch date.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Lucky_Cindy
6 months, 3 weeks agovictory108
9 months agoSteAle
10 months, 3 weeks agoLinuscai
1 year, 1 month ago