exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 197 discussion

Actual exam question from PMI's PMP
Question #: 197
Topic #: 1
[All PMP Questions]

Close to the end of a project, a customer claims that some deliverables have not been met and starts initiating change requests.
What should the project manager do next?

  • A. Refer to the requirements traceability matrix.
  • B. Escalate the change request to the project sponsor.
  • C. Revise the project scope baseline.
  • D. Review the approved project charter.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months, 2 weeks ago
Selected Answer: A
A. Refer to the requirements traceability matrix
upvoted 1 times
...
victory108
10 months, 3 weeks ago
Selected Answer: A
A. Refer to the requirements traceability matrix
upvoted 1 times
...
SteAle
11 months ago
Selected Answer: A
The requirements traceability matrix links product requirements to the deliverables that satisfy them
upvoted 2 times
...
QUSAR
11 months, 1 week ago
Selected Answer: C
C is correct answer
upvoted 2 times
...
JMCCRAY
1 year, 1 month ago
Selected Answer: A
When a customer claims that some deliverables have not been met close to the end of a project, the project manager should take the following steps: A. Refer to the requirements traceability matrix: The project manager should first review the project's requirements traceability matrix to confirm if the customer's claim is valid. The requirements traceability matrix shows the link between the project's requirements, project scope, and deliverables. By reviewing the matrix, the project manager can identify any missing deliverables or requirements that may have been overlooked.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...