Which of the following documents sets the project objectives?

  • A. Project charter
  • B. Project schedule
  • C. Project scope statement
  • D. Project organization chart
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nugi
6 months, 1 week ago
Selected Answer: A
I think should be A. Project Charter. The project charter is the primary document that formally authorizes a project and sets the project objectives. It serves as a high-level overview of the project, outlining key information such as: Project objectives and purpose
upvoted 1 times
...
Salim_7
1 year, 8 months ago
I would say A. Standards for Program Management 4th Edition, page 36 : Key elements of a program charter consist of the program scope, assumptions, constraints, high-level risks, high- level benefits, goals and objectives, success factors, timing, key stakeholders, and other provisions that tie the program to the business case, thereby enabling program strategy alignment. Page 110 : This initial program scope assessment develops the program scope statement FROM the program goals and objectives.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...