Exam PgMP topic 1 question 84 discussion

Actual exam question from PMI's PgMP
Question #: 84
Topic #: 1
[All PgMP Questions]

Which of the following documents sets the project objectives?

  • A. Project charter
  • B. Project schedule
  • C. Project scope statement
  • D. Project organization chart
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nugi
4 months, 2 weeks ago
Selected Answer: A
I think should be A. Project Charter. The project charter is the primary document that formally authorizes a project and sets the project objectives. It serves as a high-level overview of the project, outlining key information such as: Project objectives and purpose
upvoted 1 times
...
[Removed]
11 months ago
Selected Answer: A
The document that typically sets the project objectives is the Project Charter (option A). The Project Charter is a formal document that authorizes the project and provides the project manager with the authority to use organizational resources for project activities. It outlines the project objectives, purpose, scope, stakeholders, constraints, and other essential information. The project objectives stated in the charter guide the project's direction and help in aligning the efforts of the project team towards achieving specific goals.
upvoted 1 times
...
Salim_7
1 year, 6 months ago
I would say A. Standards for Program Management 4th Edition, page 36 : Key elements of a program charter consist of the program scope, assumptions, constraints, high-level risks, high- level benefits, goals and objectives, success factors, timing, key stakeholders, and other provisions that tie the program to the business case, thereby enabling program strategy alignment. Page 110 : This initial program scope assessment develops the program scope statement FROM the program goals and objectives.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.