A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?

  • A. Review the stakeholder engagement plan.
  • B. Review the resource management plan.
  • C. Review the risk management plan.
  • D. Review the communications management plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 4 weeks ago
Selected Answer: D
D. Review the communications management plan
upvoted 1 times
...
victory108
9 months, 1 week ago
Selected Answer: D
D. Review the communications management plan
upvoted 2 times
...
SteAle
10 months, 3 weeks ago
Selected Answer: D
Comm plan focuses on how the communications should be managed. In this scenario, the developer was supposed to respond. The responsibilities of the team members when it comes to the project communications are captured in the comm plan.
upvoted 1 times
...
rajeshtk
1 year ago
Correct answer is "D". The project manager need to ensure the message is received,understood and acknowledged by the receiver. Just pushing the message won't help.
upvoted 1 times
...
DRohan
1 year ago
If the developer has missed reading an e-mail, then stakeholder engagement must be reviewed, e-mail was sent to everyone, so it seams there is no requirement of reviewing communication management plan, So my answer is A.
upvoted 1 times
JNLigonde
11 months, 3 weeks ago
The developer didn’t see the email. It does not mean that they didn’t want to read the email. The communication plan should include multiple ways to reach or get the attention of stakeholders, especially at important times like that one. The communication plan would need a revision.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...