Question #: 443
Topic #: 1
[All PgMP Questions]

After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder asks the program manager to immediately include the new technology into the program.
What should the program manager do next?

  • A. Assess the new technology and discuss the results with the program steering committee to determine next steps.
  • B. Start the change management process and submit a change request to integrate the new technology.
  • C. Inform the stakeholder that the program will not be changed until proof of concept (PoC) is completed.
  • D. Research the new technology and begin its integration during the next development cycle.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
happykaur
10 months, 2 weeks ago
Selected Answer: A
In this scenario, the appropriate next step for the program manager, after an influential stakeholder suggests integrating a new technology into the program, is: A. **Assess the new technology and discuss the results with the program steering committee to determine next steps.** This approach is prudent as it involves a thorough assessment of the new technology to understand its potential impacts, benefits, and risks. Discussing these findings with the program steering committee ensures that the decision to integrate (or not) the technology is made based on informed consensus, aligning with the overall program objectives and considering the views of key stakeholders.
upvoted 1 times
...
happykaur
10 months, 2 weeks ago
Selected Answer: A
After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder asks the program manager to immediately include the new technology into the program. What should the program manager do next? A. Assess the new technology and discuss the results with the program steering committee to determine next steps. B. Start the change management process and submit a change request to integrate the new technology. C. Inform the stakeholder that the program will not be changed until proof of concept (PoC) is completed. D. Research the new technology and begin its integration during the next development cycle
upvoted 1 times
...
hanyulin
11 months, 2 weeks ago
Selected Answer: B
the answer should be B
upvoted 1 times
...
Salim_7
1 year, 6 months ago
I would go for A.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...