Exam PMP topic 1 question 214 discussion

Actual exam question from PMI's PMP
Question #: 214
Topic #: 1
[All PMP Questions]

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.
Which action should the project manager take to procure the vehicles?

  • A. Ask the technical team to revise the requirements, even if it requires extra budget.
  • B. Arrange a meeting with the client to request additional time to find a new supplier.
  • C. Review the existing service contracts to find an option to help procure the vehicles.
  • D. Procure the vehicles from another supplier and report the change to the change control board (CCB) later.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Only12go
7 months, 1 week ago
Selected Answer: C
C. Review the existing service contracts to find an option to help procure the vehicles. In this situation, the project manager should review the existing service contracts to see if there are any provisions or clauses that could help address the issue with the vehicle supplier. This may involve checking if the contract with the construction services provider has any flexibility or options for additional services, including vehicle procurement. By doing so, the project manager can explore existing contractual arrangements to find a solution that minimizes project delays and additional costs. It's essential to engage legal and contract management experts if needed to navigate the contractual terms effectively. If no contractual provisions are found, then the project manager should consider engaging the change control board (CCB) to assess and approve any necessary changes to the project's scope, schedule, or budget related to this issue.
upvoted 1 times
...
sshe0882
10 months ago
C is correct as contract can include some additional information/options for such a case. So contract should be checked first.
upvoted 1 times
...
victory108
10 months, 2 weeks ago
Selected Answer: C
C. Review the existing service contracts to find an option to help procure the vehicles
upvoted 1 times
...
TBT_1
11 months, 3 weeks ago
Selected Answer: C
C seems to be correct. D: Procuring the vehicles from another supplier without involving the change control board (CCB) would undermine proper change management processes and potentially lead to issues with contract compliance or stakeholder expectations.
upvoted 3 times
...
Orochi
1 year ago
Selected Answer: C
Only C, check any options/alternatives first
upvoted 3 times
...
mshad
1 year ago
Selected Answer: D
Given the time constraint and the inability of the original vehicle supplier to deliver, the project manager should take immediate action to procure the vehicles from an alternative supplier. This ensures that the project can continue without significant delays. Once the vehicles are procured from the new supplier, the project manager should report this change to the change control board (CCB) as part of the project's change management process. The CCB will review and assess the change to determine its impact on the project, including any potential budget or schedule adjustments. Options A and B are not suitable in this situation as revising the requirements or requesting additional time from the client would likely result in project delays. Option C, reviewing existing service contracts, may not provide a viable solution for procuring the vehicles as the contracts may not have provisions for such a situation. Therefore, the best course of action is to procure the vehicles from another supplier and report the change to the change control board for appropriate documentation and approval.
upvoted 1 times
Jamrock
10 months, 3 weeks ago
c-GPT is not always right, sir/madame
upvoted 2 times
...
AP2023S
1 year ago
Are you sure? CCB should be involved BEFORE a change, not after. CCB is created to decide if a change can be allowed, not to register one decided by someone else.
upvoted 6 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...