Exam PMP topic 1 question 690 discussion

Actual exam question from PMI's PMP
Question #: 690
Topic #: 1
[All PMP Questions]

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

  • A. Ask the financial manager to delay implementation due to potential project delays and penalties.
  • B. Assess the impact of the change and review the project management plan for next steps.
  • C. Adapt the resource management plan and ask for financial approval before sending it to the customer.
  • D. Review the project schedule to determine which technique will reduce impact on project duration.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: B
B. Assess the impact of the change and review the project management plan for next steps
upvoted 1 times
...
Scottxk1
8 months, 1 week ago
Selected Answer: B
I choose B as none of the other options seem within my authority or actual help towards a solution. If it is urgent, I need to assess the impact and follow the Project Management Plan's escaltion pathways.
upvoted 1 times
...
adviselee
11 months, 3 weeks ago
B should not be a proper answer for this question. assess the impact of the change in that urgent situation? I don't think so. I think C is closer to answer. But, this one is not perfect too.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago