exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 219 discussion

Actual exam question from PMI's PMP
Question #: 219
Topic #: 1
[All PMP Questions]

A healthcare company is in the process of deploying an innovative healthcare solution globally. The project team has completed a limited release. The stakeholders have raised concerns about global healthcare guidelines and risks.
What should the project manager do next?

  • A. Evaluate lessons learned from similar projects prior to deployment.
  • B. Perform a qualitative risk analysis on the identified project risks.
  • C. Review compliance and regulatory requirements with stakeholders.
  • D. Conduct a feasibility analysis of deploying the solution globally.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MonBouj
9 months ago
Selected Answer: C
C. Review compliance and regulatory requirements with stakeholders. Since the stakeholders have raised concerns about global healthcare guidelines and risks, it is crucial to ensure that the project aligns with all relevant compliance and regulatory requirements before proceeding further. This review will help identify potential issues and address stakeholder concerns effectively, paving the way for a smoother deployment.
upvoted 1 times
...
AirJordan
9 months ago
eview compliance and regulatory requirements with stakeholders. Ensuring that the innovative healthcare solution meets global guidelines is crucial. By aligning with stakeholders and reviewing the compliance and regulatory landscape, you can address any concerns and mitigate risks. This step is essential to ensure that the deployment proceeds smoothly and adheres to all necessary standards.
upvoted 1 times
...
Tuanit
1 year, 9 months ago
The question doesn't explicitly mention that stakeholder's concern is about "Review compliance and regulatory". So confused.
upvoted 1 times
...
victory108
2 years ago
Selected Answer: C
C. Review compliance and regulatory requirements with stakeholders
upvoted 1 times
...
Jamrock
2 years ago
Selected Answer: C
C. Review compliance and regulatory requirements with stakeholders. Explanation: In the given scenario, the project team has completed a limited release of the healthcare solution, and stakeholders have raised concerns about global healthcare guidelines and risks. To address these concerns and ensure compliance with regulations, the project manager should review the compliance and regulatory requirements with the stakeholders.
upvoted 2 times
...
Rick6797
2 years ago
Why not B?
upvoted 2 times
...
duongduy
2 years, 2 months ago
why not D
upvoted 2 times
nobia
2 years, 1 month ago
D. Conduct a feasibility analysis of deploying the solution globally is not the best choice here because the project is already in the process of global deployment. A feasibility analysis is generally conducted before starting a project or initiating a new phase, not during deployment or implementation.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...