Question #: 760
Topic #: 1
[All PMP Questions]

During the execution of a project, a key stakeholder complains to the project manager about recent communications. The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.

What should the project manager do?

  • A. Explain to the key stakeholder the way in which the project team communicates information.
  • B. Update the communications management plan to fulfill the key stakeholder's expectations about relevant information.
  • C. Send relevant information to all key stakeholders simultaneously to ensure consistent communication.
  • D. Ask the project sponsor to hold a meeting with the key stakeholder to ensure that the stakeholder is engaged in the project.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: B
B. Update the communications management plan to fulfill the key stakeholder's expectations about relevant information
upvoted 1 times
...
fulcrum501
11 months, 3 weeks ago
Selected Answer: B
different stakeholders can require different communication plans, so the discrepancy should be recorded
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago