Actual exam question from PMI's PMP
Question #: 260
Topic #: 1
[All PMP Questions]

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.
What should the project manager do?

  • A. Request additional funding from the sponsor to obtain a new resource to fill in the gap.
  • B. Inform the customer of the impact immediately and prepare for escalation.
  • C. Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.
  • D. Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Tina9900
7 months ago
Selected Answer: D
D. I thought about B but "prepare for escalation" seems to be the wrong answer and informing the customer before evaluating the impact shouldn't be done.
upvoted 1 times
...
Lucky_Cindy
1 year ago
Selected Answer: D
D. Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: D
D. Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: D
I would go with D though it doesn't seem right to readjust the schedule as it is normally fixed on Agile projects. I would have gone with B but the PM cannot inform the customer of the impact immediately. First, the impact needs to be worked out.
upvoted 1 times
...
adviselee
1 year, 5 months ago
Selected Answer: D
Is it okay that PM adjust the schedule by themselves? I understand A,B,C is not good enough for this question, but D looks not that nice
upvoted 1 times
adviselee
1 year, 5 months ago
I think B would be better.
upvoted 1 times
...
Thirukj
1 year, 4 months ago
Agile right, so yes possible to adjust schedule according to resource availability Answer is D
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago