exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 199 discussion

Actual exam question from PMI's CAPM
Question #: 199
Topic #: 1
[All CAPM Questions]

What process is included in Project Schedule Management?

  • A. Estimate Activity Durations
  • B. Create Work Breakdown Structure (WBS)
  • C. Direct and Manage Project Work
  • D. Estimate Activity Resources
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
041ba31
11 months, 1 week ago
Selected Answer: A
A. Estimate Activity Durations The process of "Estimate Activity Durations" is included in Project Schedule Management. This process, as part of the project planning phase, involves estimating the amount of time required to complete each specific activity or task in the project schedule. These duration estimates are essential for developing a realistic project schedule and timeline, which is a key component of project schedule management.
upvoted 1 times
...
eminema07
1 year, 6 months ago
Selected Answer: A
pg 173 6th edition
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago