A. Estimate Activity Durations
The process of "Estimate Activity Durations" is included in Project Schedule Management. This process, as part of the project planning phase, involves estimating the amount of time required to complete each specific activity or task in the project schedule. These duration estimates are essential for developing a realistic project schedule and timeline, which is a key component of project schedule management.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
041ba31
11 months, 1 week agoeminema07
1 year, 6 months ago