Why the other options are incorrect:
B. Create Work Breakdown Structure (WBS)
❌ Part of Project Scope Management, not Schedule Management.
C. Direct and Manage Project Work
❌ Part of Project Integration Management, focused on executing the work defined in the project plan.
D. Estimate Activity Resources
❌ Belongs to Project Resource Management, although it's often used as input to schedule estimation, it is not a Schedule Management process itself.
A. Estimate Activity Durations
The process of "Estimate Activity Durations" is included in Project Schedule Management. This process, as part of the project planning phase, involves estimating the amount of time required to complete each specific activity or task in the project schedule. These duration estimates are essential for developing a realistic project schedule and timeline, which is a key component of project schedule management.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
3 weeks, 4 days ago041ba31
1 year agoeminema07
1 year, 7 months ago