What process is performed periodically throughout the project as needed?

  • A. Plan Risk Management
  • B. Plan Communications Management
  • C. Plan Resource Management
  • D. Plan Cost Management
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: C
Key phrases: "as needed" which = Communication
upvoted 1 times
...
JesseChou_123
1 month, 4 weeks ago
Selected Answer: B
Why the others are not correct: A. Plan Risk Management – Usually performed once or at predefined points during the project. C. Plan Resource Management – Typically developed early in the project and updated only if major changes occur. D. Plan Cost Management – Generally performed once during planning and not revisited unless there's a significant change to project scope or cost strategy.
upvoted 1 times
...
Vangelis_1980
1 year ago
Selected Answer: B
B. Plan Communications Management This process involves determining the information and communication needs of the project stakeholders and defining the communication approach. As the project evolves, stakeholder needs and communication requirements can change, necessitating periodic updates to the communication plan.   The other options are typically performed once at the beginning of the project or at specific intervals, rather than continuously throughout the project life cycle.
upvoted 2 times
...
041ba31
1 year, 8 months ago
B. Plan Communications Management The process of "Plan Communications Management" is performed periodically throughout the project as needed. It involves developing and maintaining a communications management plan that guides how project communication activities will be conducted. Since communication needs and strategies can change as the project progresses, this process may be revisited and updated periodically to ensure that communication remains effective and aligned with project requirements and stakeholder needs.
upvoted 1 times
...
HPouria
1 year, 9 months ago
Selected Answer: A
The process that is performed periodically throughout the project as needed is "A. Plan Risk Management." This process involves identifying, assessing, and planning for potential risks throughout the project's lifecycle and is not a one-time activity but rather an ongoing and iterative process to address new risks as they arise.
upvoted 2 times
...
Rocket20
2 years, 1 month ago
Selected Answer: B
communications management
upvoted 1 times
...
[Removed]
2 years, 1 month ago
Selected Answer: B
PMBOK pg 366 Effectively plan on how to provide stakeholders with relevant information in a timely manner.
upvoted 1 times
...
newwen06
2 years, 1 month ago
Selected Answer: B
Plan Communications Management - This process is performed periodically throughout the project as needed. Plan Risk Management - processes should be conducted iteratively.
upvoted 4 times
...
ChymKuBoy
2 years, 1 month ago
Selected Answer: B
B for sure
upvoted 2 times
...
adingmaki
2 years, 2 months ago
Selected Answer: B
Plam communications management. reference PMBOK pg 336
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...