exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 743 discussion

Actual exam question from PMI's PMP
Question #: 743
Topic #: 1
[All PMP Questions]

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

  • A. Give the senior manager access to the product backlog.
  • B. Organize a review of the kanban board with the manager.
  • C. Contact the senior manager and discuss their needs.
  • D. Modify the PMO template to include the information.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: C
C. Contact the senior manager and discuss their needs
upvoted 1 times
...
SteAle
9 months, 1 week ago
Selected Answer: D
The first step should be to understand the stakeholder's needs.
upvoted 1 times
SteAle
9 months, 1 week ago
I meant C
upvoted 2 times
...
...
Faozi
11 months, 2 weeks ago
Selected Answer: C
I had thought of B first. But when you look at C, it's most suited because you get the details from the senior manager first.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago