Exam PMI-PBA topic 1 question 96 discussion

Actual exam question from PMI's PMI-PBA
Question #: 96
Topic #: 1
[All PMI-PBA Questions]

A business analyst has been assigned to ProjectY. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the business need?

  • A. Traceability matrix
  • B. Requirements package
  • C. Reliability matrix
  • D. Requirements management plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
qunfei
1 year ago
Selected Answer: A
Only RTM
upvoted 2 times
...
AlphaD
1 year ago
Selected Answer: A
Traceability matrix. Reliability matrix doesn't exist.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...