The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?

  • A. Use cases
  • B. Project scope
  • C. Delphi outcome
  • D. RACI chart
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
qunfei
10 months, 3 weeks ago
Selected Answer: A
Use cases show the connection between the features and test cases which has the AC inside as artifact.
upvoted 3 times
...
AlphaD
11 months, 2 weeks ago
A. Use Cases Use cases are a valuable project artifact that describe interactions between actors (users) and the system. They provide a detailed narrative of how the system should behave in specific scenarios. By reviewing the use cases, the test team can identify the expected behavior and outcomes of the system, which can be used as a basis for defining acceptance criteria.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago