A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager's emails are very harsh.
What should the project manager do to solve this situation?
oenyabine
10 months, 1 week agoLucky_Cindy
1 year, 2 months agovictory108
1 year, 4 months agoSteAle
1 year, 6 months agoThirukj
1 year, 7 months agoAP2023S
1 year, 7 months agoestimater
1 year, 2 months agobu02951
1 year, 2 months ago