A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.
How should the project manager ensure that project risks are reported accurately in the risk register?
WhiteTable
8 months, 2 weeks agoAbbasTaki
11 months, 2 weeks agovictory108
11 months, 2 weeks ago