exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 204 discussion

Actual exam question from PMI's PMP
Question #: 204
Topic #: 1
[All PMP Questions]

A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other contracting jobs because they are not part of the project team.
What should the project manager do first in this situation?

  • A. Report the issue to higher management and seek their direct involvement to complete the job from the contract department.
  • B. Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project.
  • C. Arrange several meetings with the contract department and ask them to contract the project as it is critical for project success.
  • D. Communicate with the contract manager to commit a budget for the resources required for project execution.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jordarlu
3 months, 2 weeks ago
Selected Answer: B
The answer is B in exam, but it would be A or C in real life
upvoted 1 times
...
JackyHGWG
10 months, 1 week ago
why C?
upvoted 1 times
...
Ngoc
10 months, 3 weeks ago
why B?
upvoted 1 times
...
Lucky_Cindy
1 year ago
Selected Answer: B
B. Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: B
B. Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project
upvoted 1 times
...
AbbasTaki
1 year, 5 months ago
Selected Answer: B
The correct answer is B. Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago