Exam PMP topic 1 question 157 discussion

Actual exam question from PMI's PMP
Question #: 157
Topic #: 1
[All PMP Questions]

A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business.
What should the project manager do to ensure business value is delivered early?

  • A. Create robust incentives to the team members to encourage speedy delivery
  • B. Create a detailed project plan and escalate delays to the functional managers
  • C. Break down the deliverables into sprints and deliver value incrementally
  • D. Fast track the project and monitor tasks closely to ensure timely delivery
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
9 months, 3 weeks ago
Selected Answer: C
C. Break down the deliverables into sprints and deliver value incrementally
upvoted 1 times
...
Asakthi
11 months, 3 weeks ago
C. Break down the deliverables into sprints and deliver value incrementally
upvoted 1 times
...
Muntadher
1 year ago
Selected Answer: C
C best fit
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: C
C. Break down the deliverables into sprints and deliver value incrementally
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...